Rajasthan Lets Factories Build Solar Up to 200% of Contract Demand: The Catch for Existing Plants
Rajasthan now lets a factory build captive solar of up to twice its contract demand. That is one of the most generous capacity limits in India. But a ruling this month makes one thing clear: if your plant is already running, you do not get the bigger limit automatically.
On 4 November 2026, the Rajasthan Electricity Regulatory Commission (RERC) turned down a cement maker that tried to unlock the 200% limit by cutting its contract demand. Here is what the rule says, what the ruling changes, and how a factory in Rajasthan should plan its next solar project.
What is Rajasthan's 200% captive solar rule?
Rajasthan allows new captive renewable plants, including behind-the-meter rooftop plants, of up to 200% of a consumer's contract demand. Any capacity above 100% must come with a battery.
The rule sits in the RERC (Terms and Conditions for Green Energy Open Access) Regulations, 2025, notified on 21 May 2025. GEOA stands for Green Energy Open Access. Renewable Watch reported that captive projects, "including behind-the-meter", can be sized up to 200% of contract demand.
Three points matter most for a factory:
- Battery above 100%: capacity between 100% and 200% of contract demand needs a BESS (Battery Energy Storage System) for at least 20% of the energy that extra capacity generates.
- No minimum size for captive: open access normally needs a contract demand of 100 kW or more, but the regulations remove that lower limit for captive consumers.
- Banking is limited: monthly banking is capped and charged at 8% of banked energy, and plants installed behind the meter are left out of banking altogether, as KSandK's summary of the rules notes.
The State then put the rules into practice. RERC approved a detailed GEOA procedure in December 2025.
What did RERC decide on 4 November 2026?
RERC held that existing behind-the-meter captive plants cannot automatically use the new 200% limit. To get it, they must formally move to the 2025 regulations through a one-time conversion route.
The case, reported by SolarQuarter, was filed by Shree Cement against Jaipur Vidyut Vitran Nigam Limited (JVVNL), the Jaipur discom (distribution company). The facts were simple:
- A grinding unit at Jobner had a contract demand of 7.40 MVA.
- It already ran a 7.08 MW behind-the-meter solar plant, installed in March 2023.
- In January 2026, the company asked to cut its contract demand to 3,540 kVA and offered to add a battery. At that lower demand, its existing plant would sit right at the 200% limit.
JVVNL said no. Its view was that the 200% limit was meant to add new green power, not to let an existing plant look bigger on paper by shrinking demand. The cut, it argued, would mostly lower the fixed charges the company pays.
The Commission agreed. It said the higher limit "was introduced to encourage additional renewable energy generation." It also noted that the company had raised the same idea during public consultation, where it was rejected in December 2025, and dismissed the petition as "devoid of merit."
Why does this ruling matter for my factory?
It tells you the 200% limit is a growth tool, not a billing tool. You can use it to build more solar. You cannot use it to trim your contract demand and cut fixed charges on a plant you already have.
This is the second time in a year RERC has drawn a tight line around behind-the-meter plants. In December 2025 it also refused a load-factor rebate claim for a behind-the-meter solar plant, saying that benefit was not meant for such installations.
The message for C&I (commercial and industrial) buyers is consistent. Read the rule for the purpose it was written for, and design your plant to match it. Creative readings are likely to be tested, and probably lost.
Can an existing captive solar plant still get the 200% limit?
Yes, but only by migrating to the GEOA Regulations, 2025, and meeting all their conditions. There is no shortcut through a contract demand cut.
Under Regulation 7 of the 2025 rules, existing consumers can carry on under their current agreements. A proviso lets them convert to the new regulations on a one-time basis, and any added capacity is treated as a fresh application. RERC's November order points existing plants to this same "one-time conversion mechanism."
Before you migrate, weigh what you gain against what changes:
- You can add capacity above your contract demand, but every kW above 100% needs battery storage.
- You move fully onto the new framework, including its rules on charges and banking.
- Behind-the-meter plants still get no banking, so surplus power has to be used, stored or exported under the applicable rules.
How is captive solar different from rooftop net metering in Rajasthan?
Net metering is a simpler route with a smaller cap: up to 1 MW, and no more than your sanctioned load or contract demand. Captive under GEOA allows far bigger plants but brings more conditions.
In its order of 7 February 2024, RERC raised the net metering limit from 500 kW to 1 MW, with capacity capped at the sanctioned load or contract demand, "whichever is lower." In October 2025, a third amendment to Rajasthan's distributed renewable energy regulations opened virtual and group net metering, again capped at 1 MW of total plant capacity.
If you want a refresher on how each metering type values your exported units, see our guide to net metering vs net billing vs gross metering.
| Point | Rooftop net metering | Captive under GEOA 2025 |
|---|---|---|
| Size limit | Up to 1 MW, and not above sanctioned load or contract demand | Up to 200% of contract demand |
| Battery | Not required by the cap | Required for capacity above 100% |
| Location | On your premises | Behind the meter or off-site |
| Banking | Net metering settlement | Limited, 8% charge; none for behind-the-meter |
| Best for | Most factories under 1 MW | Large, high-load sites with big roofs or land |
How should a Rajasthan factory size its next solar plant?
Start from your daytime load, not from the maximum the rules allow. A plant sized at 200% of contract demand only pays off if you can use, store or legally export that power.
Work through these steps:
- Map your daytime load. Use 12 months of bills and your load profile. Our simple sizing guide for factory rooftop solar walks through the four limits that usually decide plant size.
- Pick the route. Below 1 MW and within your sanctioned load, net metering is usually simpler. Above that, captive under GEOA opens more room.
- Price the battery honestly. Capacity above 100% only works with storage. Model the battery storage for your solar plant as part of the project, not as an add-on.
- Plan for no banking behind the meter. Size so that most generation is used on site during the day.
- Check your existing plant's status. If you already run solar, decide whether migration is worth it before planning any expansion.
Rajasthan is not alone in tying bigger plants to batteries. Maharashtra has proposed something similar, covered in our post on Maharashtra's draft battery storage rule above 100 kW. Batteries are likely to become a standard part of larger C&I solar plans across states.
Should I fund the plant myself or use an OPEX model?
The bigger and more complex the plant, the stronger the case for letting a developer carry the cost and the risk. A 200% captive plant with a battery is a large, long-term investment.
With CAPEX rooftop solar, you buy the plant, claim the savings and take on the approvals, battery sizing and performance risk yourself. With the OPEX solar model, a developer funds, builds, owns and maintains the plant, and you pay a lower per-unit tariff with zero upfront cost.
For a battery-backed plant, that split matters. The developer takes on equipment choice, regulatory paperwork and long-term upkeep, and you pay only for the power you use.
FAQ
Can a Rajasthan factory install solar above its contract demand?
Yes. Under the RERC GEOA Regulations, 2025, a new captive plant, including a behind-the-meter one, can go up to 200% of contract demand, with battery storage needed for capacity above 100%.
Does the 200% limit apply to solar plants built before 2025?
Not automatically. RERC's order of 4 November 2026 says existing behind-the-meter plants must formally migrate to the 2025 regulations through a one-time conversion to get the higher limit.
Can I reduce my contract demand to fit more solar under the 200% rule?
RERC rejected exactly this approach. It held that the 200% limit is meant to add new renewable generation, not to raise the ratio by cutting contract demand on an existing plant.
Is banking allowed for behind-the-meter solar in Rajasthan?
No. The GEOA Regulations, 2025 exclude plants installed behind the meter from banking, so surplus power has to be used on site, stored or handled under other applicable rules.
What is the rooftop net metering limit in Rajasthan?
RERC raised it to 1 MW in February 2024, capped at the consumer's sanctioned load or contract demand, whichever is lower.
About SustVest
SustVest (SolarGridX Ventures Pvt Ltd) is a rooftop solar developer in India, ranked in CRISIL's Top 10, running 80+ distributed solar plants of about 30 MW across 13 states for factories, hospitals, hotels and institutions. Under our OPEX/RESCO (Renewable Energy Service Company) model, we fund, build, own and maintain the plant, and you pay a lower per-unit tariff with zero upfront cost. Planning solar for a Rajasthan site? Talk to our team about a zero-upfront rooftop solar plan.
Sources
- SolarQuarter: RERC rejects plea to reduce contract demand for 200% captive solar capacity benefit (6 November 2026)
- RERC (Terms and Conditions for Green Energy Open Access) Regulations, 2025, Gazette text
- Renewable Watch: Rajasthan announces Green Energy Open Access Regulations, 2025
- KSandK: Rajasthan releases Green Energy Open Access Regulations, 2025
- SolarQuarter: RERC approves detailed procedure for green energy open access
- SolarQuarter: RERC rules against load factor rebate claim for behind-the-meter solar plants
- RERC order of 7 February 2024 on the rooftop net metering limit
- SolarQuarter: RERC approves third amendment to distributed renewable energy regulations